September 18, 2025
Marino Corporation reports that it will install permanent asphalt in front of Filano on University Ave on Friday, September 19, from 7-11 a.m. University Avenue will be passable for vehicular traffic and flaggers will be present. This is the final work associated with the sewer line replacement at Filano. Parking at Filano will not be impacted.
Marino Corporation is completing other work on High Street for PennDOT.
August 22, 2025
Marino Corporation reports that it will complete punch list items next, which will require flagging. Also, PennDOT is currently reviewing extra work items.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
July 11, 2025
Please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. When working, Marino Corporation will have both lane and parking restrictions in place daily between Rosedale & Miner streets.
Distribution
Initials of Personnel
Daylight Working Times 8:00 pm - 6:00 am
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
July 14 - 26, 2025
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
- Zone: Zone Striping
| Firm | Item of Work | M - 7/14 | T - 7/15 | W - 7/16 | T - 7/17 | F - 7/18 | S - 7/19 | S - 7/20 | M - 7/21 | T - 7/22 | W - 7/23 | T - 7/24 | F - 7/25 | S - 7/26 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Marino | Milling (8pm Start) | |||||||||||||
| Sharples (Profile Mill) | X | |||||||||||||
| Side Streets | X | |||||||||||||
| Marino | Exploratory Excavation 33+25 L (Daytime) | X | X | X | ||||||||||
| Marino | Base Repair (Daytime) | X | X | |||||||||||
| Marino | Curb Repair (Daytime) | X | X | X | ||||||||||
| Marino | Wearing Course (8 pm start) | X | X | X | X | |||||||||
| Zone | Permanent Striping (Daytime) | X | X | X | X | 
June 13, 2025
Please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. When working, Marino Corporation will have both lane and parking restrictions in place daily between Rosedale & Miner streets.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
June 16 - 28, 2025
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 6/16 | T - 6/17 | W - 6/18 | T - 6/19 | F - 6/20 | S - 6/21 | M - 6/23 | T - 6/24 | W - 6/25 | T - 6/26 | F - 6/27 | S - 6/28 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Marino | Sharples ADA Ramps | ||||||||||||
| Excavation | X | X | X | ||||||||||
| Concrete Placement | X | X | X | ||||||||||
| Restoration | X | X | |||||||||||
| Marino | SW High and Barnard | ||||||||||||
| Excavation | X | X | |||||||||||
| Concrete Placement | X | X | |||||||||||
| Brick Work | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
June 6, 2025
Please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. When working, Marino Corporation will have both lane and parking restrictions in place daily between Rosedale & Miner streets.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
June 9 - 21, 2025
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 6/9 | T - 6/10 | W - 6/11 | T - 6/12 | F - 6/13 | S - 6/14 | M - 6/16 | T - 6/17 | W - 6/18 | T - 6/19 | F - 6/20 | S - 6/21 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Marino | Sharples ADA Ramps | ||||||||||||
| Excavation | X | X | X | ||||||||||
| Concrete Placement | X | X | |||||||||||
| Restoration | X | X | X | ||||||||||
| Marino | SW High and Barnard | ||||||||||||
| Excavation | X | X | |||||||||||
| Concrete Placement | X | X | |||||||||||
| Brick Work | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
April 25, 2025
PennDOT will update the University soon regarding when they will start paving High Street. More information can be found on Marino Corporation's District 6 news page and its project webpage.
March 4, 2025
For this week and the week of March 10, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. When working, Marino Corporation will have both lane and parking restrictions in place daily between Rosedale & Miner streets.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
March 3 - 15, 2025
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 3/3 | T - 3/4 | W - 3/5 | T - 3/6 | F - 3/7 | S - 3/8 | M - 3/10 | T - 3/11 | W - 3/12 | T - 3/13 | F - 3/14 | S - 3/15 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | |||||||||||||
| West Chester University Events | |||||||||||||
| INLET 11 (Nields to Lacey East Side) | |||||||||||||
| Marino | Excavtion / Subbase | X | |||||||||||
| Marino | Floor Rebar / Floor Placement | X | |||||||||||
| Marino | Wall Rebar / Form Work / Wall Placement | X | |||||||||||
| Marino | Inlet Hood / Backfill / Road Base | X | |||||||||||
| Marino | Pavement / soil Restoration | X | |||||||||||
| South West Union St. | |||||||||||||
| Marino | Demo & Excavation | X | X | ||||||||||
| Marino | Stone Grade and Concrete Placement | X | X | ||||||||||
| Marino | Brick Installation | X | X | X | |||||||||
| North East Union St. | |||||||||||||
| Marino | Brick Border Edging (Approval Pending) | X | X | X | 
February 28, 2025
The new traffic light at High and University is now active; please see the photo below. It will be flashing for seven days and will then cycle normally thereafter. In addition, the new traffic light at High and Sharpless will be activated later after further roadwork. More information can be found on Marino Corporation's District 6 news page and its project webpage.
 
                              		
                              February 21, 2025
Marino Corporation has the following planned for the week of February 24:
- Monday, February 24 - No work on-site
- Tuesday, February 25 - Zone striping will eradicate and install temporary pavement markings @ Linden and University. Marino Corporation will provide traffic control.
- Wednesday, February 26 - ETC Sign Installation
- Thursday, February 27 - ETC Sign Installation
- Friday, February 28 - No work on-site
Once work has been completed on Tuesday, February 25, the activation of signals @ Linden and University will begin to be coordinated. Pending weather and Aqua completing utility work by Friday, February 28, Marino Corporation will look to remobilize to the site during the week of March 3.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
January 24, 2025
Signal activation, signage, and temporary pavement markings will be addressed at University Avenue and High Street over the next several weeks. The traffic lights at Sharpless and High streets should be operable by late spring/early summer.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
January 16, 2025
Beginning Friday, January 17, excavation and construction will begin to take place on Sharpless and High streets as part of PennDOT's High Street Safety Improvement Project in West Chester. This work is scheduled to continue over the next two weeks.
Please be aware that Sharpless Street from High Street to Reynolds Alley will be closed on Friday, January 17, from 7 a.m. – 4 p.m. In addition, the same section of Sharpless Street will be closed Thursday, January 23, through Friday, January 31. This closure will most likely have some impact on the traffic patterns of returning students. Reynolds Alley will be accessible from both University Avenue and Sharpless Street during the closures.
December 13, 2024
For the weeks of December 16 and December 23, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Marino Corporation's field operations will pause at the end of the day on December 19 and will resume on January 2.
Lenni Electrical Corporation will launch traffic signal work at Sharpless Street and University Avenue on December 20 and December 26-27; they will oversee traffic control during this time period.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
December 16 - 28, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 12/16 | T - 12/17 | W - 12/18 | T - 12/19 | F - 12/20 | S - 12/21 | M - 12/23 | T - 12/24 | W - 12/25 | T - 12/26 | F - 12/27 | S - 12/28 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | |||||||||||||
| West Chester University Events | |||||||||||||
| E. Union Street | |||||||||||||
| Marino | Demo & Excavation (SW) | X | X | H | H | H | |||||||
| Marino | Grade & Install Granite Curb (SW) | X | O | O | O | ||||||||
| Marino | Asphalt - Pavement Restoration (SW) | X | L | L | L | ||||||||
| E. Barnard Street | I | I | I | ||||||||||
| Marino | Grade & Install Granite Curb (SW) | X | X | D | D | D | |||||||
| Marino | Brick Sidewalk (SW) | X | X | X | A | A | A | ||||||
| Marino | Install & Grade 2A Subbase (SW) | X | Y | Y | Y | ||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW & SW) | X | |||||||||||
| Marino | Base Concrete / Driveway Apron (SW) | X | B | B | B | ||||||||
| Marino | Brick Sidewalk (NW) | X | R | R | R | ||||||||
| Marino | Storm Drainage (NW & SW) (Inlet Conversion) | X | X | E | E | E | |||||||
| Marino | Asphalt - Pavement Restoration (SW) | X | A | A | A | ||||||||
| Dean Street | K | K | K | ||||||||||
| Marino | Brick Sidewalk (NW) | X | |||||||||||
| Traffic Signal Work | |||||||||||||
| Lenni | Traffic Signal Mast Arms (Sharpless & University) | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Marino Corporation ceasing work for Christmas Break (12/20/24) - Resume Work 1/2/25
- Submit Price on Pour-in-Place Construction for Inlet 11
Upcoming Activites
- Exploratory Excavation / High & Dean (NW Corner)
December 6, 2024
For the weeks of December 9 and December 16, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on December 20.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
December 9 - 21, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 12/9 | T - 12/10 | W - 12/11 | T - 12/12 | F - 12/13 | S - 12/14 | M - 12/16 | T - 12/17 | W - 12/18 | T - 12/19 | F - 12/20 | S - 12/21 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | X | ||||||||||||
| West Chester University Events | |||||||||||||
| Student Move-out | X | X | X | X | |||||||||
| Fall Commencement | X | X | X | ||||||||||
| E. Union Street | |||||||||||||
| Marino | Set Inlet Conversion Slab (NE) | X | |||||||||||
| Marino | Brick Sidewalk (NW) | X | X | ||||||||||
| Marino | Asphalt - Pavement Restoration (NW) | ||||||||||||
| Marino | Demo & Excavation (SW) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SW) | X | |||||||||||
| Marino | Install & Grade 2A Subbase (SW) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (SW) | X | |||||||||||
| Marino | Brick Sidewalk (SW) | X | |||||||||||
| E. Barnard Street | |||||||||||||
| Marino | Set Inlet Conversion Slab (SE) | X | |||||||||||
| Marino | Storm Drainage (SW) (MH-06 - I-03 - I-12) | X | X | ||||||||||
| Marino | Install & Grade 2A Subbase (NW) | X | X | ||||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | X | ||||||||||
| Marino | Brick Sidewalk (NW) | X | X | ||||||||||
| Marino | Demo & Excavation (NW) | X | |||||||||||
| Marino | Storm Drainage (NW) (Inlet Conversion) | X | |||||||||||
| Marino | Demo & Excavation (SW) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SW) | X | X | ||||||||||
| Marino | Install & Grade 2A Subbase (SW) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (SW) | X | X | ||||||||||
| Marino | Brick Sidewalk (SW) | X | X | X | |||||||||
| Dean Street | |||||||||||||
| Marino | Install & Grade 2A Subbase (NW) | X | X | X | |||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | X | ||||||||||
| Marino | Brick Sidewalk (NW) | X | X | ||||||||||
| Traffic Signal Work | |||||||||||||
| Lenni | Various Corners / Conduit & Junction Box Installation | X | X | X | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Submit Price on Pour-in-Place Construction for Inlet 11
Upcoming Activites
- Exploratory Excavation / High & Dean (NW Corner)
November 22, 2024
Please be aware that Marino Corporation is scheduling the following work around the University from 11/25 - 12/6:
| Date | Item of Work | 
|---|---|
| 11/25 | University NW Excavation Linden Driveway - closed and removed (Scheduled to reopen 12/2 @ 7:30 am) | 
| 11/26 | University NW - Curb Installation Linden Driveway - Curb Installation Linden SW - Base concrete | 
| 11/27 | Linden Driveway Concrete Placement Linden SW ADA Placement University NW - Curb Installation | 
| 12/2 | 7:30 am open Linden Driveway | 
| 12/2 - 12/6 | Finish Brick and Restoration Linden and University. Construction will be significantly complete in the University area ahead of commencement | 
November 22, 2024
For the weeks of November 25 and December 2, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on November 29.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
November 25 - December 7, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 11/25 | T - 11/26 | W - 11/27 | T - 11/28 | F - 11/29 | S - 11/30 | M - 12/2 | T - 12/3 | W - 12/4 | T - 12/5 | F - 12/6 | S - 12/7 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | T | T | |||||||||||
| University Ave. | H | H | |||||||||||
| Marino | Demo & Excavation (NW) | X | A | A | |||||||||
| Marino | Grade & Install Granite Curb (NW) | X | X | N | N | ||||||||
| Marino | Base Concrete - Pavement Restoration | X | K | K | |||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | S | S | X | |||||||||
| Marino | Asphalt - Pavement Restoration | G | G | X | |||||||||
| Marino | Brick Sidewalk (NW) | I | I | X | X | ||||||||
| Linden Street | V | V | |||||||||||
| Marino | Demo @ Driveway (West Side) | X | I | I | |||||||||
| Marino | Brick Sidewalk (West Side) | X | N | N | |||||||||
| Marino | Asphalt Road Restoration (West Side) | X | G | G | |||||||||
| Marino | Grade & Install Granite Curb @ Driveway (West Side) | X | |||||||||||
| Marino | Install Driveway Apron & ADA Ramp (West Side) | X | H | H | |||||||||
| Marino | Brick Sidewalk (NW) | O | O | X | X | ||||||||
| E. Barnard Street | L | L | |||||||||||
| Marino | Demo & Excavation (NW) | X | I | I | |||||||||
| Marino | Grade & Install Granite Curb (NW) | D | D | X | |||||||||
| Marino | Asphalt - Pavement Restoration | A | A | X | |||||||||
| Marino | Brick Sidewalk (NW) | Y | Y | X | |||||||||
| Marino | Demo & Excavation (SW) | X | |||||||||||
| Dean Street | |||||||||||||
| Marino | Demo & Excavation (NW) | X | N | N | |||||||||
| Marino | Storm Drainage (NW) (MH-03 - I-6) | O | O | X | |||||||||
| Marino | Grade & Install Granite Curb (NW) | X | |||||||||||
| E. Union Street | W | W | |||||||||||
| Marino | Grade & Install Granite Curb (NW) | O | O | X | |||||||||
| Traffic Signal Work | R | R | |||||||||||
| Lenni | Various Corners / Conduit & Junction Box Installation | X | X | X | K | K | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Submit Price on Pour-in-Place Construction for Inlet 11
Upcoming Activites
November 15, 2024
Below, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on November 29.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
November 18 - 30, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 11/18 | T - 11/19 | W - 11/20 | T - 11/21 | F - 11/22 | S - 11/23 | M - 11/25 | T - 11/26 | W - 11/27 | T - 11/28 | F - 11/29 | S - 11/30 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | T | T | |||||||||||
| University Ave. | H | H | |||||||||||
| Marino | Asphalt Road Restoration (SW) | X | A | A | |||||||||
| Marino | Topsoil Restoration (SW). | X | N | N | |||||||||
| Marino | Demo & Excavation (NW) | X | K | K | |||||||||
| Marino | Grade & Install Granite Curb (NW) | X | X | S | S | ||||||||
| Marino | 2A Subbase / Base Concrete (NW) | X | G | G | |||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | I | I | |||||||||
| Linden Street | V | V | |||||||||||
| Marino | Asphalt Road Restoration (NW) | X | I | I | |||||||||
| Marino | Topsoil Restoration (NW). | X | N | N | |||||||||
| Marino | Brick Sidewalk (NW) | X | G | G | |||||||||
| Marino | Demo & Excavation (SW) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SW) | X | X | H | H | ||||||||
| Marino | Demo @ Driveway | X | O | O | |||||||||
| Marino | Grade & Install Granite Curb @ Driveway | X | L | L | |||||||||
| Marino | Base Concrete / ADA Ramp Construction (SW) | X | I | I | |||||||||
| Marino | Install Concrete Apron @ Driveway | X | D | D | |||||||||
| E. Union Street | A | A | |||||||||||
| Marino | Storm Drainage (NW) (MH-05 - I-4) | X | Y | Y | |||||||||
| Marino | Grade & Install Granite Curb (NW) | X | X | ||||||||||
| Marino | 2A Subbase / Base Concrete (NW) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | X | N | N | ||||||||
| Marino | Brick Sidewalk (NW) | X | O | O | |||||||||
| Dean Street | |||||||||||||
| Marino | Demo & Excavation (NW) | X | W | W | |||||||||
| Marino | Storm Drainage (NW) (MH-03 - I-6) | X | O | O | |||||||||
| Traffic Signal Work | R | R | |||||||||||
| Lenni | Various Corners / Conduit & Junction Box Installation | X | X | X | X | X | X | X | X | K | K | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Submit Price on Pour-in-Place Construction for Inlet 11
Upcoming Activites
November 15, 2024
Please be aware that Marino Corporation is scheduling the following work around the University for the weeks of 11/18 and 11/25:
| Date | Item of Work | 
|---|---|
| 11/18 | University SW - Paving and topsoil restoration. Corner should be open midday. Linden NW - Brick installation / paving and topsoil (anticipate having open morning of 11/19) | 
| 11/19 | University NW - Demo / Excavation | 
| 11/20 | University NW - Curb Installation Linden SW - Demo / Excavation | 
| 11/21 | University NW - Curb Installation / Subbase / Paving Linden SW - Curb Installation | 
| 11/22 | University NW - Curb Installation / Subbase / Paving Linden SW - Curb Installation / Subbase / Paving | 
| 11/25 | University NW - ADA + Base concrete placement Linden Driveway - closed and removed (Scheduled to reopen 12/2 @ 7:30 am) | 
| 11/26 | University NW - Brick Installation Linden Driveway - Curb Installation | 
| 11/27 | Linden Driveway Concrete Placement University NW - Brick Installation | 
| 12/2 | 7:30 am open Linden Driveway | 
| 12/2 - 12/6 | Finish Brick and Restoration Linden and University. Construction will be significantly complete in the University area ahead of commencement. | 
November 14, 2024
Below, please see Marino Corporation's schedule for the High Street Safety Improvement Project in West Chester. Both lane & parking restrictions will be in place daily between Rosedale & Miner Streets.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
November 11 - 22, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 11/11 | T - 11/12 | W - 11/13 | T - 11/14 | F - 11/15 | S - 11/16 | M - 11/18 | T - 11/19 | W - 11/20 | T - 11/21 | F - 11/22 | S - 11/23 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | X | ||||||||||||
| Rosedale Bumpout | |||||||||||||
| Marino | Demo & Excavation (W - Bumpout) | X | |||||||||||
| Marino | Grade & Install Granite Curb (W - Bumpout) | X | |||||||||||
| Marino | Concrete Road Restoration (W - Bumpout) | X | |||||||||||
| Marino | Asphalt Road Restoration (W - Bumpout) | X | |||||||||||
| Marino | Topsoil Restoration (W-Bumpout) | X | |||||||||||
| E. Nields Street | |||||||||||||
| Marino | Base Concrete / ADA Ramp Const. (W- Bumpout) | X | |||||||||||
| Marino | ADA Ramp Const. / Brick Sidewalk (W- Bumpout) | X | |||||||||||
| Marino | Asphalt Road Restoration (W - Bumpout) | X | |||||||||||
| Marino | Topsoil Restoration (W-Bumpout) | X | |||||||||||
| Marino | ADA Ramp Const. / Brick Sidewalk (W - Bumpout) | X | |||||||||||
| E. Union Street | |||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | X | |||||||||
| Marino | Topsoil Restoration (SE) | X | X | ||||||||||
| Marino | Grade & Install Granite Curb (NW). | X | |||||||||||
| Marino | 2A Subbase (NW) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | |||||||||||
| Marino | Concrete Road Restoration (NW). | X | |||||||||||
| Marino | Asphalt Road Restoration (NW) | X | |||||||||||
| Linden Street | |||||||||||||
| Marino | Demo & Excavation (NW) | X | X | X | |||||||||
| Marino | Grade & Install Granite Curb (NW). | X | |||||||||||
| Marino | 2A Subbase (NW) | X | |||||||||||
| Marino | Concrete Road Restoration (NW). | X | |||||||||||
| Marino | Asphalt Road Restoration (NW) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NW) | X | X | X | X | X | |||||||
| Marino | Topsoil Restoration (NW). | ||||||||||||
| University Ave. | |||||||||||||
| Marino | Demo & Excavation (SW) | X | X | ||||||||||
| Marino | Grade & Install Granite Curb (SW). | X | X | ||||||||||
| Marino | 2A Subbase (NW) | X | |||||||||||
| Marino | Concrete Road Restoration (SW) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SW) | X | X | ||||||||||
| Marino | Asphalt Road Restoration (SW) | X | |||||||||||
| Marino | Topsoil Restoration (SW). | X | |||||||||||
| Marino | Demo & Excavation (NW) | X | |||||||||||
| Barnard Street | |||||||||||||
| Marino | Demo & Excavation (NW) | X | |||||||||||
| Marino | Grade & Install Granite Curb (NW) | X | |||||||||||
| Marino | Concrete Road Restoration (NW). | X | |||||||||||
| Marino | Asphalt Road Restoration (NW) | X | X | ||||||||||
| Marino | Base Concrete / ADA Ramp Construction (NW) | X | |||||||||||
| Traffic Signal Work | |||||||||||||
| Lenni | Various Corners / Conduit & Junction Box Installation | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Discussion on Inlet 11. (Roadway 12.0 in PPCC)
Upcoming Activites
November 5, 2024
Below, please see Marino Corporation’s two-week schedule for the High Street Safety Improvement Project in West Chester. Both lane & parking restrictions will be in place daily between Rosedale & Miner Streets.
More information can be found on Marino Corporation's District 6 news page and its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
November 4 - 16, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 11/4 | T - 11/5 | W - 11/6 | T - 11/7 | F - 11/8 | S - 11/9 | S - 11/10 | M - 11/11 | T - 11/12 | W - 11/13 | T - 11/14 | F - 11/15 | S - 11/16 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | X | |||||||||||||
| Magnolia Street | ||||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | ||||||||||||
| E. Nields Street | ||||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | |||||||||||
| Marino | Demo & Excavation (W - Bumpout) | X | X | |||||||||||
| Marino | Grade & Install Granite Curb (W - Bumpout) | X | X | |||||||||||
| Marino | Concrete Road Restoration (W - Bumpout) | X | ||||||||||||
| Marino | Topsoil Restoration (W-Bumpout) | X | ||||||||||||
| E. Union Street | ||||||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | ||||||||||||
| Marino | 2A Subbase (SE) | X | ||||||||||||
| Marino | Base Concrete / ADA Ramp Construction | X | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | X | ||||||||||
| Barnard Street | ||||||||||||||
| Marino | Grade & Install Granite Curb (NW) | X | X | |||||||||||
| Marino | 2A Subbase (NW) | X | ||||||||||||
| Marino | Base Concrete / ADA Ramp Construction | X | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NW) | X | X | X | X | |||||||||
| Marino | Demo & Excavation | X | ||||||||||||
| Linden Street | ||||||||||||||
| Marino | Demo & Excavation (W - Bumpout) | X | ||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | |||||||||||
| Marino | Demo & Excavation (NW) | X | ||||||||||||
| Marino | Grade & Install Granite Curb (NW) | X | ||||||||||||
| Rosedale Bumpout | ||||||||||||||
| Marino | Demo & Excavation (W - BUmpout) | X | ||||||||||||
| Marino | Grade & Install Granite Curb (W - Bumpout) | X | X | X | ||||||||||
| Marino | Concrete Road Restoration (W - Bumpout) | X | ||||||||||||
| Marino | Topsoil Restoration (W - Bumpout) | X | ||||||||||||
| University Avenue | ||||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SW) | X | ||||||||||||
| Traffic Signal Work | ||||||||||||||
| Lenni | Various Corners / Conduit & Junction Box Installation | X | X | X | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
- Discussion on Inlet 11. (Roadway 12.0 in PPCC)
Upcoming Activites
- 11/2 - "Experience West Chester University" Event
October 29, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through November 8, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
October 28 - November 9, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 10/28 | T - 10/29 | W - 10/30 | T - 10/31 | F - 11/1 | S - 11/2 | M - 11/4 | T - 11/5 | W - 11/6 | T - 11/7 | F - 11/8 | S - 11/9 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | X | ||||||||||||
| Linden Street | |||||||||||||
| Marino | Demo & Excavation (SE) | X | X | ||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | X | X | ||||||||
| Magnolia Street | |||||||||||||
| Marino | Demo & Excavation (SE) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | |||||||||||
| Marino | Grade & Install Granite Curb (West) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | ||||||||||
| University Ave. | |||||||||||||
| Marino | Demo & Excavation (SE) | X | X | ||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | X | ||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | X | |||||||||
| E. Union Street | |||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | X | X | |||||||||
| Marino | Demo & Excavation (SE) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | |||||||||||
| Marino | Base Concrete / ADA Ramp Construction (SE) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (SE) | X | X | ||||||||||
| Barnard Street | |||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | X | X | |||||||||
| Marino | Demo & Excavation (NW) | X | |||||||||||
| Marino | Storm Drainage & Pipe (NW) | X | |||||||||||
| Marino | Grade & Install Granite Curb (NW) | X | |||||||||||
| Lacey Street | |||||||||||||
| Marino | Demo & Excavation (West) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (West) | X | X | ||||||||||
| E. Nields Street | |||||||||||||
| Marino | Demo & Excavation (NE) | X | |||||||||||
| Traffic Signal Work | |||||||||||||
| Lenni | Union & Linden - Conduit & JB Installation | X | X | X | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
- Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
- Awaiting approval of Concrete Transition Slabs
Upcoming Activites
- 11/2 - "Experience West Chester University" Event
October 22, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through November 1, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
October 21 - November 2, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 10/21 | T - 10/22 | W - 10/23 | T - 10/24 | F - 10/25 | S - 10/26 | M - 10/28 | T - 10/29 | W - 10/30 | T - 10/31 | F - 11/1 | S - 11/2 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | W | X | |||||||||||
| Linden Street | C | ||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | X | U | |||||||||
| Marino | Demo & Excavation (SE) | X | |||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | H | ||||||||||
| Marino | Prep for Base Concrete (SE) | O | X | ||||||||||
| Union Street | M | ||||||||||||
| Marino | Prep for Base Concrete (NE) | X | E | ||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | C | ||||||||||
| Marino | Base Concrete (NE) | O | X | ||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | M | X | X | |||||||||
| Marino | Demo & Excavation (SE) | I | X | X | |||||||||
| Marino | Grade & Install Granite Curb (SE) | N | X | X | |||||||||
| Barnard Street | G | ||||||||||||
| Marino | Prep for Base Concrete (NE) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | |||||||||||
| Marino | Base Concrete (NE) | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | X | ||||||||||
| E. Nields Street | |||||||||||||
| Marino | Demo & Excavation (NE) | X | X | ||||||||||
| Marino | Grade & Install Granite Curb (NE) | X | W | ||||||||||
| Marino | Prep for Base Concrete (NE) | C | X | ||||||||||
| Lacey Street | U | ||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | |||||||||
| University Ave. | H | ||||||||||||
| Marino | Demo & Excavation (SE) | X | O | ||||||||||
| Marino | Grade & Install Granite Curb (SE) | X | X | M | |||||||||
| Marino | Prep for Base Concrete (SE) | E | X | ||||||||||
| Magnolia Street | C | ||||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk (NE) | X | X | O | X | ||||||||
| Marino | Demo & Excavation (SE) | M | X | ||||||||||
| Traffic Signal Work | I | ||||||||||||
| Lenni | University - Conduit | X | X | X | X | X | N | ||||||
| Lenni | Linden - Conduit Installation | G | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
- Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
- Awaiting approval of Concrete Transition Slabs
Upcoming Activites
- 10/25 10/27 - Homecoming Weekend
October 17, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through October 25, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
October 14 - 26, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 10/14 | T - 10/15 | W - 10/16 | T - 10/17 | F - 10/18 | S - 10/19 | M - 10/21 | T - 10/22 | W - 10/23 | T - 10/24 | F - 10/25 | S - 10/26 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Progress Meeting | X | ||||||||||||
| Union Street | |||||||||||||
| Marino | 15" RCP & Inlet 05 & MH-04 | X | |||||||||||
| Marino | Excavation for Sidewalk & Curb | X | X | ||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Marino | Asphalt Base Restoration in front of Granite Curb | X | |||||||||||
| Marino | Concrete Base Restoration in front of Granite Curb | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | X | ||||||||
| Magnolia Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Marino | Concrete Base Course / Front & Rear of Granite Curb | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | X | ||||||||
| Linden Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Marino | Concrete Base Course / Front & Rear of Granite Curb | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | X | ||||||||
| Lacey Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Marino | Concrete Base Course / Front & Rear of Granite Curb | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | X | ||||||||
| Barnard Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Marino | Concrete Base Course / Front & Rear of Granite Curb | X | |||||||||||
| Marino | ADA Ramp Construction / Brick Sidewalk | X | X | X | X | ||||||||
| Traffic Signal Work (University Ave & Sharpless St.) | |||||||||||||
| Lenni | Sharpless - Sidewalk Restoration | X | |||||||||||
| Lenni | Union - Conduit Installation | X | |||||||||||
| Lenni | Price - Install Conduit | X | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
- Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
- Awaiting decision on ADA DWS Tile color
- Awaiting approval of Concrete Transition Slabs
Upcoming Activites
- 10/25 10/27 - Homecoming Weekend
October 4, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from October 7-18, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
October 7-19, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 10/7 | T - 10/8 | W - 10/9 | T - 10/10 | F - 10/11 | S - 10/12 | M - 10/14 | T - 10/15 | W - 10/16 | T - 10/17 | F - 10/18 | S - 10/19 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Barnard Street | |||||||||||||
| Marino | Sidewalk Prep / Install | X | |||||||||||
| Marino | Demo & Excavation | X | |||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Marino | Sidewalk Prep | X | |||||||||||
| University Avenue | |||||||||||||
| Marino | Sidewalk Prep | X | |||||||||||
| Marino | Install Concrete Sidewalk | X | X | ||||||||||
| E. Nields Street | |||||||||||||
| Marino | Sidewalk Prep | X | |||||||||||
| Marino | Install Concrete Sidewalk | X | X | X | |||||||||
| Linden Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Marino | Sidewalk Prep / Install | X | X | ||||||||||
| Lacey Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Marino | Sidewalk Prep | X | |||||||||||
| Magnolia Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| Linden Street | |||||||||||||
| Marino | Demo & Excavation | ||||||||||||
| Marino | Grade & Install Granite Curb | ||||||||||||
| Union Street | |||||||||||||
| Marino | 15" RCP & Inlet 05 & MH-04 | X | |||||||||||
| Marino | Demo & Excavation | X | |||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Marino | Sidewalk Prep | X | |||||||||||
| Miscellaneous | |||||||||||||
| Marino | Asphalt Base Restoration in front of Granite Curb | X | X | ||||||||||
| Traffic Signal Work (University Ave & Sharpless St.) | |||||||||||||
| Lenni | Sharpless - Sidewalk Restoration | X | X | X | X | X | X | X | X | X | X | ||
| Lenni | University - Install Conduit & Foundations | X | X | X | X | X | X | X | X | X | X | ||
| Utility Work | |||||||||||||
| Aqua | Water Service Replacement (229 High Street) | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
- Awaiting response on RFI regarding Inlet 11.
Upcoming Activites
- 10/25 10/27 - Homecoming Weekend
October 1, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through October 12, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
September 30 - October 12, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 9/30 | T - 10/1 | W - 10/2 | T - 10/3 | F - 10/4 | S - 10/5 | M - 10/7 | T - 10/8 | W - 10/9 | T - 10/10 | F - 10/11 | S - 10/12 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Lacey Street | |||||||||||||
| Marino | 15" RCP & Inlet 08 & MH-01 | X | X | X | X | ||||||||
| Magnolia Street | |||||||||||||
| Marino | Manhole Rebuild | X | |||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Miscellaneous | |||||||||||||
| Marino | Inlet 11 | X | X | ||||||||||
| Linden Street | |||||||||||||
| Marino | Demo & Excavation | X | X | ||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| University Avenue | |||||||||||||
| Marino | Demo & Excavation | X | |||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Barnard Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | |||||||||||
| E. Nields Street | |||||||||||||
| Marino | Grade & Install Granite Curb | X | X | ||||||||||
| Traffic Signal Work (University Ave & Sharpless St.) | |||||||||||||
| Lenni | Sharpless - Install Conduit & Foundations | X | X | X | |||||||||
| Lenni | University - Install Conduit & Foundations | X | X | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
Upcoming Activites
- Saturday 10/5 - "Experience West Chester University" - WCU Event
September 27, 2024
As part of the PennDOT project, its contractor, Marino Corporation, will be implementing the following parking restrictions for 9/30 - 10/4:
- Linden NE Corner, 2 spaces
- Lacey NE Corner, 2 spaces
- Nields SE corner, 2 spaces
Marino will remove parking restrictions as work is completed.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
September 13, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Both lane and parking restrictions will be in place daily between University Avenue and Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
September 16-28, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- Lenni: Lenni Electric (Traffic Signal)
| Firm | Item of Work | M - 9/16 | T - 9/17 | W - 9/18 | T - 9/19 | F - 9/20 | S - 9/21 | M - 9/23 | T - 9/24 | W - 9/25 | T - 9/26 | F - 9/27 | S - 9/28 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Lacey Street | |||||||||||||
| Marino | 15" RCP & Inlet 08 & MH-01 | X | X | X | |||||||||
| Marino | Granite Curb Installation | ||||||||||||
| E. Nields Street | |||||||||||||
| Marino | 15" RCP & Inlet 09 | X | |||||||||||
| Marino | Granite Curb Installation | X | X | ||||||||||
| Magnolia Street | |||||||||||||
| Marino | 15" RCP & Inlet 07 & MH-02 | X | |||||||||||
| Marino | Granite Curb Installation | X | X | ||||||||||
| Union Street | |||||||||||||
| Marino | Stump Removal | X | |||||||||||
| Marino | 15" RCP & Inlet 07 & MH-02 | X | X | ||||||||||
| Barnard Street | |||||||||||||
| Marino | 15" RCP & Inlet 07 & MH-02 | X | |||||||||||
| Utility Work | |||||||||||||
| Aqua | Water Service Replacement (400-500 Blk of High St.) | X | X | X | X | X | X | X | X | X | |||
| Traffic Signal Work (University Ave & Sharpless St.) | |||||||||||||
| Lenni | Layout & PA One Call Mark-out | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place between University Ave & Miner Street.
Upcoming Activites
September 10, 2024
As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 12 and September 13:
- Nields St. SE corner 1 space / NE corner 1 space
Marino Corporation will remove parking restrictions as they complete work in areas.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
September 6, 2024
As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 9 and 10:
- Nields St. SE corner 1 space
- Lacey St. NE corner 2 spaces
- Magnolia St. NE corner 2 spaces on High / 2 spaces on Magnolia
Marino Corporation will remove parking restrictions as they complete work in areas.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
September 6, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Please know that Marino Corporation will implement daily lane restrictions between University Avenue & Miner Street.
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
September 9-21, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- KB: Knight Brothers (Tree Rem)
- Chesco: Chesco Sawcutting
| Item of Work | M - 9/9 | T - 9/10 | W - 9/11 | T - 9/12 | F - 9/13 | S - 9/14 | M - 9/16 | T - 9/17 | W - 9/18 | T - 9/19 | F - 9/20 | S - 9/21 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Entire Project | ||||||||||||
| Pipe & Precast Inlet Delivery | X | |||||||||||
| Granite Curb Delivery | X | X | X | X | ||||||||
| E. Nields Street | ||||||||||||
| Demo SE Corner | X | |||||||||||
| 15" RCP & Inlet 09 | X | |||||||||||
| Granite Curb Installation | X | |||||||||||
| Lacey Street | ||||||||||||
| Demo NE Corner | X | X | ||||||||||
| 15" RCP & Inlet 08 & MH-01 | X | |||||||||||
| Magnolia Street | ||||||||||||
| Demo NE Corner | X | X | ||||||||||
| 15" RCP & Inlet 07 & MH-02 | X | |||||||||||
| Union Street | ||||||||||||
| Demo NE Corner | X | X | ||||||||||
| 15" RCP & Inlet 07 & MH-02 | X | |||||||||||
| Barnard Street | ||||||||||||
| Demo NE Corner | X | |||||||||||
| 15" RCP & Inlet 07 & MH-02 | X | |||||||||||
| Traffic Signal Work (University Ave & Sharpless St.) | ||||||||||||
| Install Conduit and Signal Foundations | X | X | X | X | X | 
Notes:
- Daily Lane Restrictions will be in place between University Ave & Miner Street.
Upcoming Activites
September 5, 2024
On behalf of PennDOT's High Street project, Marino Corporation has posted the following traffic restrictions for the week of September 9, 2024:
- Nields St. to Barnard St. one lane road (flagging) / shifts from 9 am to 3 pm
More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
September 4, 2024
On behalf of PennDOT's High Street project, Marino Corporation has posted the following parking restrictions to prepare for saw cutting on Friday, September 6:
- University Ave. SW corner 1 spot / NW corner 1 spot
- Nield St. to University Ave Southbound No Parking all spots
- Linden St. NW corner 1 spot
- South of Linden St. Southbound 3 spots
Marino Corporation will clear parking restrictions as they complete areas. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
September 4, 2024
As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester, which commenced on September 3. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.
Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm
Two Week Schedule
PennDOT
West Chester / High Street SIP
ECMS 115425
September 2-14, 2024
Contractors
- Marino: Marino Corporation
- Horizon: Horizon Engineers (Survey)
- KB: Knight Brothers (Tree Rem)
- Chesco: Chesco Sawcutting
| Item of Work | M - 9/2 | T - 9/3 | W - 9/4 | T - 9/5 | F - 9/6 | S - 9/7 | M - 9/9 | T - 9/10 | W - 9/11 | T - 9/12 | F - 9/13 | S - 9/14 | 
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Entire Project | L | |||||||||||
| Tree Removal (229 S. High Street) | A | X | X | |||||||||
| Tree Trimming | B | X | X | |||||||||
| Survey & Layout | O | X | X | X | ||||||||
| Sawcut Pavement | R | X | X | |||||||||
| Pipe & Precast Inlet Delivery | X | |||||||||||
| Granite Curb Delivery | X | X | X | X | ||||||||
| E. Nields Street | D | |||||||||||
| Demo SE Corner | A | X | ||||||||||
| 15" RCP & Inlet 09 | Y | X | X | |||||||||
| Lacey Street | ||||||||||||
| Demo NE Corner | X | |||||||||||
| 15" RCP & Inlet 08 & MH-01 | X | X | ||||||||||
| Magnolia Street | ||||||||||||
| Demo NE Corner | X | |||||||||||
| 15" RCP & Inlet 07 & MH-02 | X | X | 
Upcoming Activities
- Demo & Drainage, NE Corner of Union St.
- Demo & Drainage, NE Corner of Barnard St.
August, 30, 2024
Dear WCU Community,
As the Chester County region has grown, so has increased traffic on local roadways and byways. The era of growth in our region prompts a heightened focus on making the entire community safer for pedestrians and motorists.
West Chester University continues to advocate for the safety of all students, faculty, staff, and visitors to its campus. Most recently, the University improved pedestrian safety at West Rosedale Avenue and South Church Street by adding a new traffic signal, crossing lights and signage, as well as a designated crosswalk.
Of equal concern is the safety of those both driving on High Street and crossing it as pedestrians, including the many members of our University community. Over the years, the University has been in regular communication with West Chester Borough, PennDOT, and Pennsylvania officials regarding safety along High Street. Our advocacy and PennDOT’s recognition of this issue has resulted in the imminent inception of a High Street Pedestrian Improvement Project. This project will improve pedestrian safety along the High Street corridor by implementing safety enhancements aimed at reducing the occurrences of crashes involving vehicles and pedestrians. Construction will begin this fall from Miner Street to Rosedale Avenue.
As part of the PennDOT project, its contractor, Marino Corporation, will conduct tree trimming /removal operations on Tuesday, September 3, and Wednesday, September 4. For this work, Marino Corporation will need to restrict parking from 9 a.m. to 3 p.m. in the following areas: southbound High Street from Sharpless Street to Nields Street North and southbound High Street from Union Street to Bernard Street northbound of High Street from Bernard Street to Miner Street. Parking restrictions will be removed as Marino Corporation moves through.
Of particular interest to the University community are the upcoming plans for the High Street intersections with Rosedale Avenue, plus Linden, University, Nields, and Sharpless streets. Among the improvements are:
- placement of additional traffic signals at University Avenue and Sharpless Street;
- installation of a left-turn lane on northbound High Street at Sharpless Street;
- installation of a left-turn lane on southbound High Street at Nields Street;
- improvements to signage and intersection lighting;
- improvements for public transit riders that include bus shelters and
- curb extensions and ADA ramps at several intersections to reduce the time required for pedestrians to cross.
Work is being coordinated with the University to reduce the impact on traffic and pedestrians, especially during WCU’s annual and special events including Homecoming, commencements, etc. During construction, one lane of traffic along High Street will be maintained and shifted as necessary so that restrictions to traffic flow are minimized.
The University participates in regular progress meetings with the contractor, the borough and PennDOT. Campus updates will be issued as needed to inform all constituents regarding traffic pattern shifts, pedestrian crossing changes, project timing, and other factors that may impact pedestrians and motorists navigating through and around our campus.
PennDOT expects the entire project to be completed in January 2026.
Please check the WCU homepage and the Ram Report for important updates to the High Street Pedestrian Improvement Project.
Learn more about the High Street Corridor Study, from which these improvements were developed.
Please see the attached media release from PennDot
Sincerely,
Zebulun R. Davenport, Ed.D.
Vice President for University Advancement and External Affairs

Todd E. Murphy 
Vice President for Finance and Administration

PennDOT Updates

FOR IMMEDIATE RELEASE
August 29, 2024
MEDIA CONTACT: Krys Johnson, krysjohnso@pa.gov
PennDOT to Begin Business U.S. 322 (High Street) Safety Improvement Project in West Chester Borough
King of Prussia, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that construction is scheduled to begin on Tuesday, September 3, for a project to improve safety at the intersections along the Business U.S. 322 (High Street) corridor in West Chester Borough and West Goshen Township, Chester County.
Under this contract, PennDOT's contractor will install new traffic signals at University Avenue and Sharpless Street and provide signal support and related equipment. The project will consist of the installation of retroreflective backplates on existing signals, modern LED luminaries, pedestrian countdown timers at signalized intersections, curb extensions, high-visibility crosswalks, drainage improvements, and comprehensive full-depth pavement restoration, culminating in a complete roadway resurfacing.
This project includes the intersections of Rosedale Avenue, Linden Street, University Avenue, Nields Street, Sharpless Street, Lacey Street, Route 52 (Price Street), Magnolia Street, Dean Street, Union Street, Barnard Street, and Route 842 (Miner Street).
This project aims to improve the efficiency of intersections for the traveling public via vehicular and pedestrian means and to reduce the occurrence of crashes involving vehicles, bicycles, and pedestrians.
Beginning Tuesday, September 3, through Friday, September 6, from 9:00 AM to 3:00 PM, periodic lane closures are scheduled on Business U.S. 322 (High Street) between Rosedale Avenue and Route 842 (Miner Street) for tree removal operations.
Motorists are advised to allow extra time when traveling near and through the work area because backups and delays will occur. All scheduled activities are weather dependent.
Marino Corporation of Skippack, Pennsylvania, is the general contractor on the $2,619,998 project which is financed with 100 percent federal funds. Physical construction on the project is expected to finish in winter 2026.
Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.
For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties, visit the District 6 Traffic Bulletin.
Subscribe to PennDOT news and traffic alerts in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties at www.penndot.pa.gov/District6.
Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.
Follow PennDOT on X and like the department on Facebook and Instagram.
