PennDOT Press Release 2024

December 13, 2024

For the weeks of December 16 and December 23, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Marino Corporation's field operations will pause at the end of the day on December 19 and will resume on January 2.

Lenni Electrical Corporation will launch traffic signal work at Sharpless Street and University Avenue on December 20 and December 26-27; they will oversee traffic control during this time period.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
December 16 - 28, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 12/16 T - 12/17 W - 12/18 T - 12/19 F - 12/20 S - 12/21 M - 12/23 T - 12/24 W - 12/25 T - 12/26 F - 12/27 S - 12/28
  Progress Meeting                        
  West Chester University Events                        
  E. Union Street                        
Marino Demo & Excavation (SW) X X         H H H      
Marino Grade & Install Granite Curb (SW)     X       O O O      
Marino Asphalt - Pavement Restoration (SW)       X     L L L      
  E. Barnard Street             I I I      
Marino Grade & Install Granite Curb (SW) X X         D D D      
Marino Brick Sidewalk (SW) X   X X     A A A      
Marino Install & Grade 2A Subbase (SW)   X         Y Y Y      
Marino Base Concrete / ADA Ramp Construction (NW & SW)   X                    
Marino Base Concrete / Driveway Apron (SW)     X       B B B      
Marino Brick Sidewalk (NW)     X       R R R      
Marino Storm Drainage (NW & SW) (Inlet Conversion)     X X     E E E      
Marino Asphalt - Pavement Restoration (SW)       X     A A A      
  Dean Street             K K K      
Marino Brick Sidewalk (NW) X                      
  Traffic Signal Work                        
Lenni Traffic Signal Mast Arms (Sharpless & University) X X X X X         X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Marino Corporation ceasing work for Christmas Break (12/20/24) - Resume Work 1/2/25
  • Submit Price on Pour-in-Place Construction for Inlet 11

Upcoming Activites

  • Exploratory Excavation / High & Dean (NW Corner)

 


December 6, 2024

For the weeks of December 9 and December 16, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on December 20.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
December 9 - 21, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 12/9 T - 12/10 W - 12/11 T - 12/12 F - 12/13 S - 12/14 M - 12/16 T - 12/17 W - 12/18 T - 12/19 F - 12/20 S - 12/21
  Progress Meeting       X                
  West Chester University Events                        
  Student Move-out   X X X X              
  Fall Commencement       X X X            
  E. Union Street                        
Marino Set Inlet Conversion Slab (NE) X                      
Marino Brick Sidewalk (NW) X X                    
Marino Asphalt - Pavement Restoration (NW)                        
Marino Demo & Excavation (SW)         X              
Marino Grade & Install Granite Curb (SW)               X        
Marino Install & Grade 2A Subbase (SW)                 X      
Marino Base Concrete / ADA Ramp Construction (SW)                 X      
Marino Brick Sidewalk (SW)                   X    
  E. Barnard Street                        
Marino Set Inlet Conversion Slab (SE) X                      
Marino Storm Drainage (SW) (MH-06 - I-03 - I-12) X X                    
Marino Install & Grade 2A Subbase (NW)   X X                  
Marino Base Concrete / ADA Ramp Construction (NW)   X X                  
Marino Brick Sidewalk (NW)     X X                
Marino Demo & Excavation (NW)     X                  
Marino Storm Drainage (NW) (Inlet Conversion)     X                  
Marino Demo & Excavation (SW)       X                
Marino Grade & Install Granite Curb (SW)         X   X          
Marino Install & Grade 2A Subbase (SW)             X          
Marino Base Concrete / ADA Ramp Construction (SW)             X X        
Marino Brick Sidewalk (SW)               X X X    
  Dean Street                        
Marino Install & Grade 2A Subbase (NW)   X X X                
Marino Base Concrete / ADA Ramp Construction (NW)     X X                
Marino Brick Sidewalk (NW)       X X              
  Traffic Signal Work                        
Lenni Various Corners / Conduit & Junction Box Installation X X X X X   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Submit Price on Pour-in-Place Construction for Inlet 11

Upcoming Activites

  • Exploratory Excavation / High & Dean (NW Corner)

 


November 22, 2024

Please be aware that Marino Corporation is scheduling the following work around the University from 11/25 - 12/6:

Date Item of Work
11/25

University NW Excavation

Linden Driveway - closed and removed (Scheduled to reopen 12/2 @ 7:30 am)

11/26

University NW - Curb Installation

Linden Driveway - Curb Installation

Linden SW - Base concrete

11/27

Linden Driveway Concrete Placement

Linden SW ADA Placement

University NW - Curb Installation

12/2

7:30 am open Linden Driveway

12/2 - 12/6

Finish Brick and Restoration Linden and University. Construction will be significantly complete in the University area ahead of commencement


November 22, 2024

For the weeks of November 25 and December 2, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on November 29.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
November 25 - December 7, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 11/25 T - 11/26 W - 11/27 T - 11/28 F - 11/29 S - 11/30 M - 12/2 T - 12/3 W - 12/4 T - 12/5 F - 12/6 S - 12/7
  Progress Meeting       T T              
  University Ave.       H H              
Marino Demo & Excavation (NW) X     A A              
Marino Grade & Install Granite Curb (NW)   X X N N              
Marino Base Concrete - Pavement Restoration     X K K              
Marino Base Concrete / ADA Ramp Construction (NW)       S S     X        
Marino Asphalt - Pavement Restoration       G G       X      
Marino Brick Sidewalk (NW)       I I         X X  
  Linden Street       V V              
Marino Demo @ Driveway (West Side) X     I I              
Marino Brick Sidewalk (West Side) X     N N              
Marino Asphalt Road Restoration (West Side) X     G G              
Marino Grade & Install Granite Curb @ Driveway (West Side)   X                    
Marino Install Driveway Apron & ADA Ramp (West Side)     X H H              
Marino Brick Sidewalk (NW)       O O     X X      
  E. Barnard Street       L L              
Marino Demo & Excavation (NW)   X   I I              
Marino Grade & Install Granite Curb (NW)       D D   X          
Marino Asphalt - Pavement Restoration       A A       X      
Marino Brick Sidewalk (NW)       Y Y           X  
Marino Demo & Excavation (SW)                     X  
  Dean Street                        
Marino Demo & Excavation (NW)   X   N N              
Marino Storm Drainage (NW) (MH-03 - I-6)       O O   X          
Marino Grade & Install Granite Curb (NW)               X        
  E. Union Street       W W              
Marino Grade & Install Granite Curb (NW)       O O         X    
  Traffic Signal Work       R R              
Lenni Various Corners / Conduit & Junction Box Installation X X X K K   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Submit Price on Pour-in-Place Construction for Inlet 11

Upcoming Activites

 


November 15, 2024

Below, please see Marino Corporation's two-week schedule for the High Street Safety Improvement Project in West Chester. Lane and parking restrictions will be in place daily between Rosedale & Miner Streets. Crews are not planning to work on November 29.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
November 18 - 30, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 11/18 T - 11/19 W - 11/20 T - 11/21 F - 11/22 S - 11/23 M - 11/25 T - 11/26 W - 11/27 T - 11/28 F - 11/29 S - 11/30
  Progress Meeting                   T T  
  University Ave.                   H H  
Marino Asphalt Road Restoration (SW) X                 A A  
Marino Topsoil Restoration (SW). X                 N N  
Marino Demo & Excavation (NW)   X               K K  
Marino Grade & Install Granite Curb (NW)     X X           S S  
Marino 2A Subbase / Base Concrete (NW)       X           G G  
Marino Base Concrete / ADA Ramp Construction (NW)             X     I I  
  Linden Street                   V V  
Marino Asphalt Road Restoration (NW) X                 I I  
Marino Topsoil Restoration (NW). X                 N N  
Marino Brick Sidewalk (NW) X                 G G  
Marino Demo & Excavation (SW)     X                  
Marino Grade & Install Granite Curb (SW)       X X         H H  
Marino Demo @ Driveway             X     O O  
Marino Grade & Install Granite Curb @ Driveway               X   L L  
Marino Base Concrete / ADA Ramp Construction (SW)               X   I I  
Marino Install Concrete Apron @ Driveway                 X D D  
  E. Union Street                   A A  
Marino Storm Drainage (NW) (MH-05 - I-4) X                 Y Y  
Marino Grade & Install Granite Curb (NW)   X X                  
Marino 2A Subbase / Base Concrete (NW)       X                
Marino Base Concrete / ADA Ramp Construction (NW)         X   X     N N  
Marino Brick Sidewalk (NW)             X     O O  
  Dean Street                        
Marino Demo & Excavation (NW)               X   W W  
Marino Storm Drainage (NW) (MH-03 - I-6)                 X O O  
  Traffic Signal Work                   R R  
Lenni Various Corners / Conduit & Junction Box Installation X X X X X   X X X K K  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Submit Price on Pour-in-Place Construction for Inlet 11

Upcoming Activites

 


November 15, 2024

Please be aware that Marino Corporation is scheduling the following work around the University for the weeks of 11/18 and 11/25:

Date Item of Work
11/18

University SW - Paving and topsoil restoration. Corner should be open midday.

Linden NW - Brick installation / paving and topsoil (anticipate having open morning of 11/19)

11/19

University NW - Demo / Excavation

11/20

University NW - Curb Installation

Linden SW - Demo / Excavation

11/21

University NW - Curb Installation / Subbase / Paving Linden SW - Curb Installation

11/22

University NW - Curb Installation / Subbase / Paving Linden SW - Curb Installation / Subbase / Paving

11/25

University NW - ADA + Base concrete placement Linden Driveway - closed and removed (Scheduled to reopen 12/2 @ 7:30 am)

11/26

University NW - Brick Installation

Linden Driveway - Curb Installation

11/27

Linden Driveway Concrete Placement

University NW - Brick Installation

12/2

7:30 am open Linden Driveway

12/2 - 12/6

Finish Brick and Restoration Linden and University. Construction will be significantly complete in the University area ahead of commencement.


November 14, 2024

Below, please see Marino Corporation’s schedule for the High Street Safety Improvement Project in West Chester. Both lane & parking restrictions will be in place daily between Rosedale & Miner Streets.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
November 11 - 22, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 11/11 T - 11/12 W - 11/13 T - 11/14 F - 11/15 S - 11/16 M - 11/18 T - 11/19 W - 11/20 T - 11/21 F - 11/22 S - 11/23
  Progress Meeting       X                
  Rosedale Bumpout                        
Marino Demo & Excavation (W - Bumpout) X                      
Marino Grade & Install Granite Curb (W - Bumpout) X                      
Marino Concrete Road Restoration (W - Bumpout) X                      
Marino Asphalt Road Restoration (W - Bumpout)   X                    
Marino Topsoil Restoration (W-Bumpout)   X                    
  E. Nields Street                        
Marino Base Concrete / ADA Ramp Const. (W- Bumpout) X                      
Marino ADA Ramp Const. / Brick Sidewalk (W- Bumpout)   X                    
Marino Asphalt Road Restoration (W - Bumpout)   X                    
Marino Topsoil Restoration (W-Bumpout)   X                    
Marino ADA Ramp Const. / Brick Sidewalk (W - Bumpout)     X                  
  E. Union Street                        
Marino ADA Ramp Construction / Brick Sidewalk (SE) X X X                  
Marino Topsoil Restoration (SE)   X X                  
Marino Grade & Install Granite Curb (NW).                   X    
Marino 2A Subbase (NW)                     X  
Marino Base Concrete / ADA Ramp Construction (NW)                     X  
Marino Concrete Road Restoration (NW).                     X  
Marino Asphalt Road Restoration (NW)                     X  
  Linden Street                        
Marino Demo & Excavation (NW) X X X                  
Marino Grade & Install Granite Curb (NW).       X                
Marino 2A Subbase (NW)       X                
Marino Concrete Road Restoration (NW).       X                
Marino Asphalt Road Restoration (NW)         X              
Marino Base Concrete / ADA Ramp Construction (NW)             X          
Marino ADA Ramp Construction / Brick Sidewalk (NW) X X X         X X      
Marino Topsoil Restoration (NW).                        
  University Ave.                        
Marino Demo & Excavation (SW) X X                    
Marino Grade & Install Granite Curb (SW).     X X                
Marino 2A Subbase (NW)       X                
Marino Concrete Road Restoration (SW)       X                
Marino ADA Ramp Construction / Brick Sidewalk (SW)       X X              
Marino Asphalt Road Restoration (SW)         X              
Marino Topsoil Restoration (SW).             X          
Marino Demo & Excavation (NW)                 X      
  Barnard Street                        
Marino Demo & Excavation (NW)         X              
Marino Grade & Install Granite Curb (NW)             X          
Marino Concrete Road Restoration (NW).             X          
Marino Asphalt Road Restoration (NW)               X     X  
Marino Base Concrete / ADA Ramp Construction (NW)                   X    
  Traffic Signal Work                        
Lenni Various Corners / Conduit & Junction Box Installation             X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Discussion on Inlet 11. (Roadway 12.0 in PPCC)

Upcoming Activites

 


November 5, 2024

Below, please see Marino Corporation’s two-week schedule for the High Street Safety Improvement Project in West Chester. Both lane & parking restrictions will be in place daily between Rosedale & Miner Streets.

More information can be found on Marino Corporation's District 6 news page and its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
November 4 - 16, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 11/4 T - 11/5 W - 11/6 T - 11/7 F - 11/8 S - 11/9 S - 11/10 M - 11/11 T - 11/12 W - 11/13 T - 11/14 F - 11/15 S - 11/16
  Progress Meeting                     X    
  Magnolia Street                          
Marino ADA Ramp Construction / Brick Sidewalk (SE) X                        
  E. Nields Street                          
Marino ADA Ramp Construction / Brick Sidewalk (SE) X X                      
Marino Demo & Excavation (W - Bumpout) X   X                    
Marino Grade & Install Granite Curb (W - Bumpout)       X X                
Marino Concrete Road Restoration (W - Bumpout)                   X      
Marino Topsoil Restoration (W-Bumpout)                     X    
  E. Union Street                          
Marino Grade & Install Granite Curb (SE) X                        
Marino 2A Subbase (SE)   X                      
Marino Base Concrete / ADA Ramp Construction       X X                
Marino ADA Ramp Construction / Brick Sidewalk (SE)         X     X X        
  Barnard Street                          
Marino Grade & Install Granite Curb (NW)   X X                    
Marino 2A Subbase (NW)     X                    
Marino Base Concrete / ADA Ramp Construction       X X                
Marino ADA Ramp Construction / Brick Sidewalk (NW)         X     X X X      
Marino Demo & Excavation                   X      
  Linden Street                          
Marino Demo & Excavation (W - Bumpout)   X                      
Marino ADA Ramp Construction / Brick Sidewalk (SE)     X X                  
Marino Demo & Excavation (NW)                     X    
Marino Grade & Install Granite Curb (NW)                       X  
  Rosedale Bumpout                          
Marino Demo & Excavation (W - BUmpout)   X                      
Marino Grade & Install Granite Curb (W - Bumpout)         X     X X        
Marino Concrete Road Restoration (W - Bumpout)                   X      
Marino Topsoil Restoration (W - Bumpout)                     X    
  University Avenue                          
Marino ADA Ramp Construction / Brick Sidewalk (SW)     X                    
  Traffic Signal Work                          
Lenni Various Corners / Conduit & Junction Box Installation X X X X X     X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Rosedale & Miner Street.
  • Discussion on Inlet 11. (Roadway 12.0 in PPCC)

Upcoming Activites

  • 11/2 - "Experience West Chester University" Event

 


October 29, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through November 8, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
October 28 - November 9, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 10/28 T - 10/29 W - 10/30 T - 10/31 F - 11/1 S - 11/2 M - 11/4 T - 11/5 W - 11/6 T - 11/7 F - 11/8 S - 11/9
  Progress Meeting       X                
  Linden Street                        
Marino Demo & Excavation (SE) X X                    
Marino Grade & Install Granite Curb (SE)     X                  
Marino ADA Ramp Construction / Brick Sidewalk (SE)       X X   X X        
  Magnolia Street                        
Marino Demo & Excavation (SE) X                      
Marino Grade & Install Granite Curb (SE)   X                    
Marino Grade & Install Granite Curb (West)       X                
Marino ADA Ramp Construction / Brick Sidewalk (SE)       X X              
  University Ave.                        
Marino Demo & Excavation (SE) X X                    
Marino Grade & Install Granite Curb (SE)   X X                  
Marino ADA Ramp Construction / Brick Sidewalk (SE)       X X   X          
  E. Union Street                        
Marino ADA Ramp Construction / Brick Sidewalk (NE) X X X                  
Marino Demo & Excavation (SE)         X              
Marino Grade & Install Granite Curb (SE)             X          
Marino Base Concrete / ADA Ramp Construction (SE)                 X      
Marino ADA Ramp Construction / Brick Sidewalk (SE)                   X X  
  Barnard Street                        
Marino ADA Ramp Construction / Brick Sidewalk (NE) X X X                  
Marino Demo & Excavation (NW)             X          
Marino Storm Drainage & Pipe (NW)               X        
Marino Grade & Install Granite Curb (NW)                   X    
  Lacey Street                        
Marino Demo & Excavation (West)   X                    
Marino ADA Ramp Construction / Brick Sidewalk (West)               X X      
  E. Nields Street                        
Marino Demo & Excavation (NE)                     X  
  Traffic Signal Work                        
Lenni Union & Linden - Conduit & JB Installation X X X X X   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
  • Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
  • Awaiting approval of Concrete Transition Slabs

Upcoming Activites

  • 11/2 - "Experience West Chester University" Event

 


October 22, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through November 1, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
October 21 - November 2, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 10/21 T - 10/22 W - 10/23 T - 10/24 F - 10/25 S - 10/26 M - 10/28 T - 10/29 W - 10/30 T - 10/31 F - 11/1 S - 11/2
  Progress Meeting           W       X    
  Linden Street           C            
Marino ADA Ramp Construction / Brick Sidewalk (NE) X X       U            
Marino Demo & Excavation (SE)     X                  
Marino Grade & Install Granite Curb (SE)       X   H            
Marino Prep for Base Concrete (SE)           O X          
  Union Street           M            
Marino Prep for Base Concrete (NE) X         E            
Marino ADA Ramp Construction / Brick Sidewalk (NE)         X C            
Marino Base Concrete (NE)           O X          
Marino ADA Ramp Construction / Brick Sidewalk (NE)           M   X X      
Marino Demo & Excavation (SE)           I     X X    
Marino Grade & Install Granite Curb (SE)           N       X X  
  Barnard Street           G            
Marino Prep for Base Concrete (NE) X                      
Marino ADA Ramp Construction / Brick Sidewalk (NE)         X              
Marino Base Concrete (NE)               X        
Marino ADA Ramp Construction / Brick Sidewalk (NE)                   X X  
  E. Nields Street                        
Marino Demo & Excavation (NE) X X                    
Marino Grade & Install Granite Curb (NE)         X W            
Marino Prep for Base Concrete (NE)           C X          
  Lacey Street           U            
Marino ADA Ramp Construction / Brick Sidewalk   X X X                
  University Ave.           H            
Marino Demo & Excavation (SE)   X       O            
Marino Grade & Install Granite Curb (SE)       X X M            
Marino Prep for Base Concrete (SE)           E X          
  Magnolia Street           C            
Marino ADA Ramp Construction / Brick Sidewalk (NE)       X X O X          
Marino Demo & Excavation (SE)           M   X        
  Traffic Signal Work           I            
Lenni University - Conduit X X X X X N            
Lenni Linden - Conduit Installation           G X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
  • Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
  • Awaiting approval of Concrete Transition Slabs

Upcoming Activites

  • 10/25 10/27 - Homecoming Weekend

 


October 17, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through October 25, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will continue to be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
October 14 - 26, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 10/14 T - 10/15 W - 10/16 T - 10/17 F - 10/18 S - 10/19 M - 10/21 T - 10/22 W - 10/23 T - 10/24 F - 10/25 S - 10/26
  Progress Meeting       X                
  Union Street                        
Marino 15" RCP & Inlet 05 & MH-04 X                      
Marino Excavation for Sidewalk & Curb X X                    
Marino Grade & Install Granite Curb     X                  
Marino Asphalt Base Restoration in front of Granite Curb       X                
Marino Concrete Base Restoration in front of Granite Curb             X          
Marino ADA Ramp Construction / Brick Sidewalk               X X X X  
  Magnolia Street                        
Marino Grade & Install Granite Curb X                      
Marino Concrete Base Course / Front & Rear of Granite Curb             X          
Marino ADA Ramp Construction / Brick Sidewalk               X X X X  
  Linden Street                        
Marino Grade & Install Granite Curb X                      
Marino Concrete Base Course / Front & Rear of Granite Curb         X              
Marino ADA Ramp Construction / Brick Sidewalk               X X X X  
  Lacey Street                        
Marino Grade & Install Granite Curb X                      
Marino Concrete Base Course / Front & Rear of Granite Curb         X              
Marino ADA Ramp Construction / Brick Sidewalk               X X X X  
  Barnard Street                        
Marino Grade & Install Granite Curb   X X                  
Marino Concrete Base Course / Front & Rear of Granite Curb         X              
Marino ADA Ramp Construction / Brick Sidewalk               X X X X  
  Traffic Signal Work (University Ave & Sharpless St.)                        
Lenni Sharpless - Sidewalk Restoration X                      
Lenni Union - Conduit Installation   X                    
Lenni Price - Install Conduit     X X X   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
  • Awaiting response on RFI regarding Inlet 11. (Roadway 12.0 in PPCC)
  • Awaiting decision on ADA DWS Tile color
  • Awaiting approval of Concrete Transition Slabs

Upcoming Activites

  • 10/25 10/27 - Homecoming Weekend

 


October 4, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from October 7-18, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
October 7-19, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 10/7 T - 10/8 W - 10/9 T - 10/10 F - 10/11 S - 10/12 M - 10/14 T - 10/15 W - 10/16 T - 10/17 F - 10/18 S - 10/19
  Barnard Street                        
Marino Sidewalk Prep / Install X                      
Marino Demo & Excavation               X        
Marino Grade & Install Granite Curb                 X X    
Marino Sidewalk Prep                     X  
  University Avenue                        
Marino Sidewalk Prep X                      
Marino Install Concrete Sidewalk     X X                
  E. Nields Street                        
Marino Sidewalk Prep X                      
Marino Install Concrete Sidewalk   X X X                
  Linden Street                        
Marino Grade & Install Granite Curb X X                    
Marino Sidewalk Prep / Install       X X              
  Lacey Street                        
Marino Grade & Install Granite Curb         X              
Marino Sidewalk Prep                     X  
  Magnolia Street                        
Marino Grade & Install Granite Curb         X              
  Linden Street                        
Marino Demo & Excavation                        
Marino Grade & Install Granite Curb                        
  Union Street                        
Marino 15" RCP & Inlet 05 & MH-04             X          
Marino Demo & Excavation               X        
Marino Grade & Install Granite Curb                 X X    
Marino Sidewalk Prep                     X  
  Miscellaneous                        
Marino Asphalt Base Restoration in front of Granite Curb             X       X  
  Traffic Signal Work (University Ave & Sharpless St.)                        
Lenni Sharpless - Sidewalk Restoration X X X X X   X X X X X  
Lenni University - Install Conduit & Foundations X X X X X   X X X X X  
  Utility Work                        
Aqua Water Service Replacement (229 High Street)       X                

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
  • Awaiting response on RFI regarding Inlet 11.

Upcoming Activites

  • 10/25 10/27 - Homecoming Weekend

 


October 1, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through October 12, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 30 - October 12, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 9/30 T - 10/1 W - 10/2 T - 10/3 F - 10/4 S - 10/5 M - 10/7 T - 10/8 W - 10/9 T - 10/10 F - 10/11 S - 10/12
  Lacey Street                        
Marino 15" RCP & Inlet 08 & MH-01 X X             X X    
  Magnolia Street                        
Marino Manhole Rebuild X                      
Marino Grade & Install Granite Curb                   X X  
  Miscellaneous                        
Marino Inlet 11   X X                  
  Linden Street                        
Marino Demo & Excavation     X X                
Marino Grade & Install Granite Curb             X          
  University Avenue                        
Marino Demo & Excavation       X                
Marino Grade & Install Granite Curb       X X              
  Barnard Street                        
Marino Grade & Install Granite Curb         X              
  E. Nields Street                        
Marino Grade & Install Granite Curb             X X        
  Traffic Signal Work (University Ave & Sharpless St.)                        
Lenni Sharpless - Install Conduit & Foundations X X X                  
Lenni University - Install Conduit & Foundations       X X   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.

Upcoming Activites

  • Saturday 10/5 - "Experience West Chester University" - WCU Event

 


September 27, 2024

As part of the PennDOT project, its contractor, Marino Corporation, will be implementing the following parking restrictions for 9/30 - 10/4:

  • Linden NE Corner, 2 spaces
  • Lacey NE Corner, 2 spaces
  • Nields SE corner, 2 spaces

Marino will remove parking restrictions as work is completed.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 13, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Both lane and parking restrictions will be in place daily between University Avenue and Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 16-28, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 9/16 T - 9/17 W - 9/18 T - 9/19 F - 9/20 S - 9/21 M - 9/23 T - 9/24 W - 9/25 T - 9/26 F - 9/27 S - 9/28
  Lacey Street                        
Marino 15" RCP & Inlet 08 & MH-01 X               X X    
Marino Granite Curb Installation                        
  E. Nields Street                        
Marino 15" RCP & Inlet 09   X                    
Marino Granite Curb Installation               X X      
  Magnolia Street                        
Marino 15" RCP & Inlet 07 & MH-02     X                  
Marino Granite Curb Installation                   X X  
  Union Street                        
Marino Stump Removal       X                
Marino 15" RCP & Inlet 07 & MH-02       X X              
  Barnard Street                        
Marino 15" RCP & Inlet 07 & MH-02             X          
  Utility Work                        
 Aqua Water Service Replacement (400-500 Blk of High St.)   X X X X   X X X X X  
  Traffic Signal Work
(University Ave & Sharpless St.)
                       
Lenni Layout & PA One Call Mark-out X X X X X              

Notes:

  • Daily Lane Restrictions will be in place between University Ave & Miner Street.

Upcoming Activites

 


September 10, 2024

As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 12 and September 13:

  • Nields St. SE corner 1 space / NE corner 1 space

Marino Corporation will remove parking restrictions as they complete work in areas.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 6, 2024

As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 9 and 10:

  • Nields St. SE corner 1 space
  • Lacey St. NE corner 2 spaces
  • Magnolia St. NE corner 2 spaces on High / 2 spaces on Magnolia

Marino Corporation will remove parking restrictions as they complete work in areas.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 6, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Please know that Marino Corporation will implement daily lane restrictions between University Avenue & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 9-21, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • KB: Knight Brothers (Tree Rem)
  • Chesco: Chesco Sawcutting
Item of Work M - 9/9 T - 9/10 W - 9/11 T - 9/12 F - 9/13 S - 9/14 M - 9/16 T - 9/17 W - 9/18 T - 9/19 F - 9/20 S - 9/21
Entire Project                        
Pipe & Precast Inlet Delivery X                      
Granite Curb Delivery   X X X X              
E. Nields Street                        
Demo SE Corner X                      
15" RCP & Inlet 09         X              
Granite Curb Installation                     X  
Lacey Street                        
Demo NE Corner X X                    
15" RCP & Inlet 08 & MH-01             X          
Magnolia Street                        
Demo NE Corner   X X                  
15" RCP & Inlet 07 & MH-02               X        
Union Street                        
Demo NE Corner     X X                
15" RCP & Inlet 07 & MH-02                 X      
Barnard Street                        
Demo NE Corner       X                
15" RCP & Inlet 07 & MH-02                   X    
Traffic Signal Work
(University Ave & Sharpless St.)
                       
Install Conduit and Signal Foundations             X X X X X  

Notes:

  • Daily Lane Restrictions will be in place between University Ave & Miner Street.

Upcoming Activites

 


September 5, 2024

On behalf of PennDOT's High Street project, Marino Corporation has posted the following traffic restrictions for the week of September 9, 2024:

  • Nields St. to Barnard St. one lane road (flagging) / shifts from 9 am to 3 pm

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 4, 2024

On behalf of PennDOT's High Street project, Marino Corporation has posted the following parking restrictions to prepare for saw cutting on Friday, September 6:

  • University Ave. SW corner 1 spot / NW corner 1 spot
  • Nield St. to University Ave Southbound No Parking all spots
  • Linden St. NW corner 1 spot
  • South of Linden St. Southbound 3 spots

Marino Corporation will clear parking restrictions as they complete areas. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 4, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester, which commenced on September 3. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 2-14, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • KB: Knight Brothers (Tree Rem)
  • Chesco: Chesco Sawcutting
Item of Work M - 9/2 T - 9/3 W - 9/4 T - 9/5 F - 9/6 S - 9/7 M - 9/9 T - 9/10 W - 9/11 T - 9/12 F - 9/13 S - 9/14
Entire Project L                      
Tree Removal (229 S. High Street) A X X                  
Tree Trimming B X X                  
Survey & Layout O   X X X              
Sawcut Pavement R     X X              
Pipe & Precast Inlet Delivery             X          
Granite Curb Delivery               X X X X  
E. Nields Street D                      
Demo SE Corner A           X          
15" RCP & Inlet 09 Y           X X        
Lacey Street                        
Demo NE Corner               X        
15" RCP & Inlet 08 & MH-01                 X X    
Magnolia Street                        
Demo NE Corner                 X      
15" RCP & Inlet 07 & MH-02                   X X  

Upcoming Activities

  • Demo & Drainage, NE Corner of Union St.
  • Demo & Drainage, NE Corner of Barnard St.

 


August, 30, 2024
Dear WCU Community,

As the Chester County region has grown, so has increased traffic on local roadways and byways. The era of growth in our region prompts a heightened focus on making the entire community safer for pedestrians and motorists.

West Chester University continues to advocate for the safety of all students, faculty, staff, and visitors to its campus. Most recently, the University improved pedestrian safety at West Rosedale Avenue and South Church Street by adding a new traffic signal, crossing lights and signage, as well as a designated crosswalk.

Of equal concern is the safety of those both driving on High Street and crossing it as pedestrians, including the many members of our University community. Over the years, the University has been in regular communication with West Chester Borough, PennDOT, and Pennsylvania officials regarding safety along High Street. Our advocacy and PennDOT’s recognition of this issue has resulted in the imminent inception of a High Street Pedestrian Improvement Project. This project will improve pedestrian safety along the High Street corridor by implementing safety enhancements aimed at reducing the occurrences of crashes involving vehicles and pedestrians. Construction will begin this fall from Miner Street to Rosedale Avenue.

As part of the PennDOT project, its contractor, Marino Corporation, will conduct tree trimming /removal operations on Tuesday, September 3, and Wednesday, September 4. For this work, Marino Corporation will need to restrict parking from 9 a.m. to 3 p.m. in the following areas: southbound High Street from Sharpless Street to Nields Street North and southbound High Street from Union Street to Bernard Street northbound of High Street from Bernard Street to Miner Street. Parking restrictions will be removed as Marino Corporation moves through.

Of particular interest to the University community are the upcoming plans for the High Street intersections with Rosedale Avenue, plus Linden, University, Nields, and Sharpless streets. Among the improvements are:

  • placement of additional traffic signals at University Avenue and Sharpless Street;
  • installation of a left-turn lane on northbound High Street at Sharpless Street;
  • installation of a left-turn lane on southbound High Street at Nields Street;
  • improvements to signage and intersection lighting;
  • improvements for public transit riders that include bus shelters and
  • curb extensions and ADA ramps at several intersections to reduce the time required for pedestrians to cross.

Work is being coordinated with the University to reduce the impact on traffic and pedestrians, especially during WCU’s annual and special events including Homecoming, commencements, etc. During construction, one lane of traffic along High Street will be maintained and shifted as necessary so that restrictions to traffic flow are minimized.

The University participates in regular progress meetings with the contractor, the borough and PennDOT. Campus updates will be issued as needed to inform all constituents regarding traffic pattern shifts, pedestrian crossing changes, project timing, and other factors that may impact pedestrians and motorists navigating through and around our campus.

PennDOT expects the entire project to be completed in January 2026.

Please check the WCU homepage and the Ram Report for important updates to the High Street Pedestrian Improvement Project.

Learn more about the High Street Corridor Study, from which these improvements were developed.

Please see the attached media release from PennDot

Sincerely,

Zebulun R. Davenport, Ed.D.
Vice President for University Advancement and External Affairs

WCU West Chester University logo

Todd E. Murphy
Vice President for Finance and Administration

WCU West Chester University logo

 


PennDOT Updates

Pennsylvania Department of Transportation logo

FOR IMMEDIATE RELEASE

August 29, 2024

MEDIA CONTACT: Krys Johnson, krysjohnso@pa.gov

PennDOT to Begin Business U.S. 322 (High Street) Safety Improvement Project in West Chester Borough

King of Prussia, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that construction is scheduled to begin on Tuesday, September 3, for a project to improve safety at the intersections along the Business U.S. 322 (High Street) corridor in West Chester Borough and West Goshen Township, Chester County.

Under this contract, PennDOT's contractor will install new traffic signals at University Avenue and Sharpless Street and provide signal support and related equipment. The project will consist of the installation of retroreflective backplates on existing signals, modern LED luminaries, pedestrian countdown timers at signalized intersections, curb extensions, high-visibility crosswalks, drainage improvements, and comprehensive full-depth pavement restoration, culminating in a complete roadway resurfacing.

This project includes the intersections of Rosedale Avenue, Linden Street, University Avenue, Nields Street, Sharpless Street, Lacey Street, Route 52 (Price Street), Magnolia Street, Dean Street, Union Street, Barnard Street, and Route 842 (Miner Street).

This project aims to improve the efficiency of intersections for the traveling public via vehicular and pedestrian means and to reduce the occurrence of crashes involving vehicles, bicycles, and pedestrians.

Beginning Tuesday, September 3, through Friday, September 6, from 9:00 AM to 3:00 PM, periodic lane closures are scheduled on Business U.S. 322 (High Street) between Rosedale Avenue and Route 842 (Miner Street) for tree removal operations.

Motorists are advised to allow extra time when traveling near and through the work area because backups and delays will occur. All scheduled activities are weather dependent.

Marino Corporation of Skippack, Pennsylvania, is the general contractor on the $2,619,998 project which is financed with 100 percent federal funds. Physical construction on the project is expected to finish in winter 2026.

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.

For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties, visit the District 6 Traffic Bulletin.

Subscribe to PennDOT news and traffic alerts in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties at www.penndot.pa.gov/District6.

Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.

Follow PennDOT on X and like the department on Facebook and Instagram.